The stages of finishing a villa, from shell to handover
The right order for finishing a villa: design and survey, services, ceilings and partitions, floors, cladding and paint, lighting, then facades and handover.
Arkan Almajara team · · 2 min read
The short answer
Finishing a villa is a chain of stages, each depending on the one before: design and survey first, then services, then ceilings and partitions, then floors and cladding, then paint and lighting, then facades and handover. The costliest mistake is starting a stage before the decisions it needs are approved.
- Design and decisions come before the first worker on site.
- Services come before whatever covers them, and are photographed before closing.
- Wet and dusty work comes before sensitive finishes.
- Facades are coordinated with exterior lighting before cladding.
A finished concrete shell looks close to habitable, but ahead of it lie dozens of decisions and stages that must come in the right order. The wrong order means demolishing what has been done.
The stages in order
| Stage | What happens | What must come before |
|---|---|---|
| 1. Design and survey | Measured survey, design, visualisation, drawings | — |
| 2. Services | Power, plumbing, AC, networks | Approved layout and lighting |
| 3. Render and waterproofing | Walls, roofs, waterproofing | Services in the walls |
| 4. Ceilings and partitions | Gypsum board, levels, light coves | Services above ceilings inspected |
| 5. Floors | Tiles, marble or timber | Wet and dusty work done |
| 6. Cladding | Marble and wood alternatives, feature walls | Backing inside walls |
| 7. Paint | Preparation, primer, coats | Ceilings and cladding |
| 8. Lighting and fittings | Downlights, strips, chandeliers, switches | First coat of paint |
| 9. Facades and exterior | Cladding, exterior lights, green walls | Exterior services |
| 10. Handover | Snags, cleaning, the file | — |
Decisions that must come first
- Room and furniture layout, because it sets sockets and lighting.
- Ceiling and lighting design.
- Positions of the TV, heavy chandeliers and wall-hung cabinets (backing).
- AC unit positions and access panels.
Read why 3D visualisation before finishing.
Photograph before closing
Everything that will be covered is photographed: services in walls, above ceilings, and backing. These photos are your reference for twenty years.
Facades
On the facades of two villas, we started before the cladding: blockwork and stone on the ground floor, then the frame, then wood alternative on the upper volumes. Read facade cladding.
Read villa finishing budget and how to choose a finishing contractor. The service: villa and home finishing.
Frequently asked questions
Can a villa be finished in phases to suit the budget?
Yes, by deciding what must be completed together (such as services and ceilings on one floor) and what can wait without later demolition (such as some cladding and furniture).
When should lighting be chosen?
Before the ceilings, because light coves, downlight positions and drivers are part of the ceiling design and its services.