The snag list and handover: receiving your project without missing a thing
How to prepare a snag list at handover: what to check in ceilings, walls, paint, lighting and doors, how to record each item, and what the handover file should contain.
Arkan Almajara team · · 2 min read
The short answer
A snag list records the small defects found at handover, each with a photo and location, closed item by item before final handover. Inspect with side light, by day and night, and test every switch and door. Receive with it a file of as-built drawings, materials and warranties.
- Inspect room by room, in order: ceiling, walls, floor, openings, electrics.
- Side light (a lamp or window light) reveals what cannot be seen from the middle.
- Every snag with a photo, a number and a location.
- The handover file is part of handover, not an extra.
Handover day is a happy day, but it is also the last easy chance to fix small defects before they become part of daily life.
What to check
| Element | What you are looking for |
|---|---|
| Ceilings | Visible joints, ripples under side light, straight edges |
| Walls | Scratches, marks, uneven sheen, true corners |
| Paint | Full coverage at corners, around switches and above skirtings |
| Cladding | Even joints, finished edges, protective film removed |
| Lighting | Every circuit works, no flicker, one colour temperature |
| Doors and joinery | Close without rubbing, handles secure |
| Electrics | Every socket and switch works, plates straight |
| Access panels | Open and close, and are where they should be |
How to check
- In order: room by room, from ceiling to floor.
- With side light: a hand lamp parallel to the surface reveals ripples. Read jointing.
- By day and night: artificial light reveals what daylight does not.
- Test everything: every switch, door, drawer and lighting scene.
Recording
Each snag: a number, a photo, a location (room and wall), a short description, who is responsible, and a date to close it. Then a photo after the fix.
The handover file
- As-built drawings.
- The finish schedule: materials, colours and codes.
- Locations of drivers and access panels.
- Photos of what is behind walls and ceilings before closing.
- Warranties and care instructions. Read care after handover.
The service: villa and home finishing.
Frequently asked questions
Should I accept handover before all snags are closed?
A partial handover is possible if the snags are minor and do not prevent use, with a signed list of what remains and a date to close it.
What should the handover file contain?
As-built drawings, material types and colour codes, locations of drivers and access panels, photos of what is behind walls and ceilings, and warranties and care instructions.