The snag list and handover: receiving your project without missing a thing

How to prepare a snag list at handover: what to check in ceilings, walls, paint, lighting and doors, how to record each item, and what the handover file should contain.

Arkan Almajara team · · 2 min read

Illustrative photo Close-up of a roller on a white wall

The short answer

A snag list records the small defects found at handover, each with a photo and location, closed item by item before final handover. Inspect with side light, by day and night, and test every switch and door. Receive with it a file of as-built drawings, materials and warranties.

  • Inspect room by room, in order: ceiling, walls, floor, openings, electrics.
  • Side light (a lamp or window light) reveals what cannot be seen from the middle.
  • Every snag with a photo, a number and a location.
  • The handover file is part of handover, not an extra.

Handover day is a happy day, but it is also the last easy chance to fix small defects before they become part of daily life.

What to check

Element What you are looking for
Ceilings Visible joints, ripples under side light, straight edges
Walls Scratches, marks, uneven sheen, true corners
Paint Full coverage at corners, around switches and above skirtings
Cladding Even joints, finished edges, protective film removed
Lighting Every circuit works, no flicker, one colour temperature
Doors and joinery Close without rubbing, handles secure
Electrics Every socket and switch works, plates straight
Access panels Open and close, and are where they should be

How to check

  1. In order: room by room, from ceiling to floor.
  2. With side light: a hand lamp parallel to the surface reveals ripples. Read jointing.
  3. By day and night: artificial light reveals what daylight does not.
  4. Test everything: every switch, door, drawer and lighting scene.

Recording

Each snag: a number, a photo, a location (room and wall), a short description, who is responsible, and a date to close it. Then a photo after the fix.

The handover file

  • As-built drawings.
  • The finish schedule: materials, colours and codes.
  • Locations of drivers and access panels.
  • Photos of what is behind walls and ceilings before closing.
  • Warranties and care instructions. Read care after handover.

The service: villa and home finishing.

Frequently asked questions

Should I accept handover before all snags are closed?

A partial handover is possible if the snags are minor and do not prevent use, with a signed list of what remains and a date to close it.

What should the handover file contain?

As-built drawings, material types and colour codes, locations of drivers and access panels, photos of what is behind walls and ceilings, and warranties and care instructions.

Share

Related service

Need this on your project?

From plan to keys: ceilings, partitions, cladding, paint, lighting and facades, with one contractor and one programme.

Turnkey Interior Fit-Out
13

Turnkey villa and apartment finishing

From plan to keys: ceilings, partitions, cladding, paint, lighting and facades, with one contractor and one programme.

Details

Have a space or a drawing? Start with a site visit.

Tell us the type of space and its approximate size, and we will get back to you to book a time.