Working as finishing contractor under a main contractor: what changes

How a finishing contractor works within a project led by a main contractor: shared programme, coordination, safety rules, reports and handover.

Arkan Almajara team · · 2 min read

During works Buffet back wall in timber with mosaic panels, pendants still wrapped

The short answer

Within a larger project, we become one link in a chain: our programme is part of the project's, our area overlaps with other trades, and the main contractor sets the site and safety rules. Success here is punctuality, clear coordination and records that make handover easy.

  • The programme is tied to the project's: our delay delays others.
  • Daily coordination with services and other trades is essential.
  • Safety rules, permits and area handover are set by the main contractor.
  • Daily reports and photos make handover and payments easier.

In dining halls for a hotel group, we worked as the finishing contractor within a larger project. That experience differs from working directly for an owner: responsibilities are clearer, deadlines stricter.

What changes

Working directly for the owner Under a main contractor
Programme Ours Part of the project programme
Site We organise it The main contractor organises it
Safety Our rules The site’s rules and permits
Coordination With the owner With several trades daily
Handover To the owner To the main contractor, then the owner
Payments With the owner Through the main contractor

Before starting

  • Written handover of the area, its condition recorded in photos.
  • Approved drawings, in their latest revision.
  • Interfaces: when services finish, when furniture comes in.
  • Space for storage and cutting.
  • Requirements: permits, protective equipment, working hours.

During the works

  • Regular coordination meetings.
  • Daily reports of labour, progress and obstacles.
  • Photos of every stage, especially before closing up.
  • Any clash raised at once, in writing.

Handover

A snag list from the main contractor, closed item by item, then the area handed back clean with the materials file and photos. Read the snag list and handover.

Read the fit-out programme and designing hotel dining halls. The service: commercial fit-out.

Frequently asked questions

Have you worked as a subcontractor?

Yes. We built dining halls and buffets for a hotel group as the finishing contractor within a larger project, working to the site's rules and programme.

What do you need from the main contractor to start?

A handed-over, ready work area, approved drawings, clear coordination points, storage space, and the interface programme with other trades.

Share

Related service

Need this on your project?

Restaurants, hotels, clinics, shops and offices, from frame and partitions to cladding and light, with one contractor.

Entrance lobby with timber cladding, marble walls and a multi-level gypsum ceiling
12

Commercial interior fit-out

Restaurants, hotels, clinics, shops and offices, from frame and partitions to cladding and light, with one contractor.

Details

Have a space or a drawing? Start with a site visit.

Tell us the type of space and its approximate size, and we will get back to you to book a time.